For: Finance and equipment leads at operators taking a proven format to a new metro area or region, and dealers asked to equip the first site.
The decision: Whether a candidate market and building can carry the format as designed, or which parts of it, from the equipment mix to the staffing model and service plan, must change before the lease is signed.
60-second answer: Demographics are a screen, not the test. Check what a lease fixes first: clear height against the manufacturer’s published dimensions, floor capacity from an engineer, and the code path from the local building official. Price labor locally: BLS puts the national median for fitness trainers and instructors at $22.67 an hour (May 2025), but metro estimates and minimum wages differ. Use Census business counts knowing what they include, and name the technicians who will service the site before specifying equipment.
Fixed variables first: the building
Regional fitness equipment growth depends on whether a format that worked in one place survives the move, and the variables that decide it are local. Some are fixed for the term of a lease; settle those first, because no equipment choice corrects them later.
- Clear height. Measure below the lowest obstruction (ducts, sprinkler heads, light fittings) at each proposed rack line and overhead-work area. Compare it with the overall height the manufacturer publishes for each candidate rack or rig, and ask the manufacturer for any clearance it specifies above the unit.
- Column spacing. Lay the planned rack rows and cardio banks, with their published clearances, over the column grid.
- Floor capacity. On an upper level, or for heavy plate storage and platforms, the structural engineer decides; see what the engineer needs before an upper-floor install.
- Code path. Model codes such as the International Building Code and International Existing Building Code are published by the International Code Council (ICC) and take effect through a jurisdiction’s ordinance, regulation or law. ICC’s adoption guidance says the adopting law should state where a model code is adopted “with amendments or changes.” Ask the architect and the local building official which occupancy classification applies to the fitness use, and whether converting the building’s use triggers upgrades to egress, fire protection, plumbing fixtures or accessibility under the locally adopted codes. The code official decides.
- Power and access. Electrical capacity and the delivery route are also fixed; see cardio electrical requirements.
Labor: wage data, wage floors and the specialist pool
Staffing cost is set by the local labor market, so price it from local data rather than carrying it over from the existing site.
National reference. The Bureau of Labor Statistics reports that the median annual wage for fitness trainers and instructors was $47,160 in May 2025, or $22.67 an hour. “The median wage is the wage at which half the workers in an occupation earned more than that amount and half earned less.”
Metro estimates. BLS publishes May 2025 Occupational Employment and Wage Statistics (OEWS) for metropolitan and nonmetropolitan areas. Pull them for each candidate market for exercise trainers and group fitness instructors (occupation code 39-9031) and for the desk and cleaning roles you staff. OEWS wages are “straight-time, gross pay, exclusive of premium pay.” They include base rates, commissions and tips, and exclude overtime, shift differentials, year-end bonuses and employer benefit costs. The survey “does not cover the self-employed,” so trainers working as independent contractors are outside the estimate.
Wage floors. The US Department of Labor’s state minimum wage table, updated July 1, 2026, shows how far floors diverge. New York lists $17.00 for New York City, Nassau, Suffolk and Westchester counties and $16.00 for the rest of the state. Texas adopts the federal minimum of $7.25 by reference. California and Washington note that their minimum wage is adjusted annually by formula. The table also warns: “Some local governments set minimum wage rates higher than their respective state minimum wage.” Those rates are not shown, so check the city and county as well as the state, along with any scheduled increases over the lease term.
The specialist pool. Wage data does not show whether qualified coaches are available. If the format depends on coached classes or zones, test recruiting before signing and decide what the format becomes if the role cannot be filled.
Competitors, catchment and peak shape
Business counts. The Census Bureau’s County Business Patterns (CBP) provides establishment counts, employment and payroll for businesses with paid employees, at national, state, county and ZIP code levels. The most recent year is 2023, released June 26, 2025. Gyms fall under industry 713940, Fitness and Recreational Sports Centers, whose definition covers facilities “featuring exercise and other active physical fitness conditioning or recreational sports activities, such as swimming, skating, or racquet sports.” Its examples include gymnasiums and physical fitness centers, but also ice or roller skating rinks, tennis club facilities and swimming pools. A CBP count is therefore not a gym count, leaves out businesses without paid employees, and says nothing about format, size, price or quality. Use it to size the field, then build a named list; reading a competitor’s opening covers above-board competitor observation.
Positions, not counts. Map which price and format positions are occupied and by whom. An empty position may be unmet demand or a price the market has not sustained; check local news for operators that opened and closed.
Commuting and peaks. Census surveys including the American Community Survey ask about the working population’s commutes: “when their trip starts, how they get there, and how long it takes.” Compare the candidate market’s commuting with your existing site’s, then visit at the hours you expect to be busy and watch how people arrive. Set machine counts from your own check-in history, adjusted for what you find, not from a ratio carried over from the last site.
Service coverage before specification
Identical machines can have different effective availability in two markets if technician coverage differs. Before specifying, ask each supplier or dealer in writing for the named technicians and base locations covering the address, response terms, and where parts are stocked; choosing a distributor by delivery, install and service capacity sets out the checks. Where coverage is thin, FEX’s view is to reduce model variety, duplicate the highest-use stations and agree a site spares kit before the first order. If the region will hold several sites, decide which parts of the specification are fixed across them, as in multi-site equipment standards.
Market fit test
Each row pairs a variable with the record that answers it. The “transfers” and “needs to change” columns are FEX analysis.
| Variable | Record or source | Format transfers when | Format needs to change when |
|---|---|---|---|
| Clear height | Measured at rack lines; manufacturer’s published dimensions | Specified racks and planned overhead work fit | Rigs or overhead stations do not fit |
| Floor capacity | Structural engineer’s assessment | Loads confirmed for the planned layout | Heavy storage or platforms need reinforcement or relocation |
| Code path | Architect and local building official | Occupancy confirmed and upgrade scope priced | A change of use triggers unpriced upgrades |
| Trainer and coach wages | OEWS metro estimates; local job postings | The staffing model costs within plan | Specialist roles are unaffordable or unfillable |
| Wage floor | State and local minimum wage, with scheduled increases | Staffed hours fit at known rates | Scheduled increases break the staffed-hours model |
| Competitor positions | CBP 713940 count, then a named list | Your intended position is open or defensible | The position is occupied, or an empty one is unexplained |
| Catchment and peaks | ACS commuting data; peak-hour visits; your check-in history | Visit pattern resembles the existing site’s | Sharper or shifted peaks change machine counts |
| Service coverage | Named technicians, response terms, parts location | Coverage confirmed in writing | Coverage is thin: consolidate models and add spares |
What to do this week
- Measure clear height at every proposed rack line and compare it with the manufacturer’s published dimensions for the specified models.
- Ask the architect and local building official about occupancy, change-of-use upgrades and the adopted code editions.
- Pull OEWS May 2025 metro estimates for code 39-9031 and your desk roles, and check state, city and county minimum wages with scheduled increases.
- Download the CBP count for industry 713940 in the candidate counties or ZIP codes, then build a named competitor list.
- Get named technician coverage, response terms and parts location in writing from each supplier before specifying.
Continue with FEX
- What to check before entering a new market
- In-house or contracted equipment service
- Checking the lease and building before ordering
FEX editorial guidance: the market fit test, the service-coverage approach and the order of checks are FEX analysis. Wage, minimum wage and business-count figures come from the cited federal sources with their dates; confirm local wage rules with counsel or the local labor agency. The building official and engineer of record decide code and structural questions, and manufacturer documentation controls equipment dimensions and clearances. This guide is not based on an interview with a named business.
Source notes
- US Bureau of Labor Statistics: Occupational Outlook Handbook, Fitness Trainers and Instructors (last modified August 27, 2026) — May 2025 median wage, median definition, occupation code.
- US Bureau of Labor Statistics: OEWS Tables (last modified May 15, 2026) — May 2025 metropolitan and nonmetropolitan area estimates.
- US Bureau of Labor Statistics: OEWS Frequently Asked Questions (accessed October 8, 2026) — Wage definition; self-employed not covered.
- US Department of Labor: State Minimum Wage Laws (updated July 1, 2026) — Federal, New York, Texas, California and Washington entries; local rates not shown.
- US Census Bureau: 2023 County Business Patterns Now Available (June 26, 2025) — Coverage of businesses with paid employees; geographic levels.
- US Census Bureau: County Business Patterns (page revised August 5, 2026) — 2023 as the most current data year.
- US Census Bureau: NAICS 713940 Fitness and Recreational Sports Centers (2017 and 2022 NAICS; accessed October 8, 2026) — Definition and examples.
- US Census Bureau: Commuting (page revised June 15, 2026) — ACS commuting questions.
- International Code Council: Code Adoption Resources (accessed October 8, 2026) — Adoption by ordinance or law, with amendments.
Editorial update, October 9, 2026: Removed the two-market composite narrative and unsupported claims about catchments, peaks, wage floors and technician density, and replaced them with checks against current federal data: BLS May 2025 wage estimates, the Labor Department’s July 1, 2026 state minimum wage table and Census 2023 County Business Patterns. Added the model-code and local-adoption distinction, and removed a shared stock photograph and unrelated OSHA and association links.